Summary
Nearly $5 million in Measure A bond money went to road construction (Bid Package 3), plus $987,611 for construction management and a CEQA exemption for Geer Road — part of $18.6 million budgeted for road work this year.
At a glance
- Total mentions
- 4
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Sep 22, 2026.
Impact analysis
About $6.4 million in Measure A road spending approved in one night.
Drivers and residents on streets getting repaved and repaired.
Mentions & discussions (3)
City Council - Sep 22, 2026
The roads program has completed 21.28 miles and $55.2 million in construction, but staff acknowledged the $1.5 million annual maintenance fund is just seed money and will need to grow as construction tapers. A second bond issuance is under discussion.
City Council - Mar 10, 2026
Nearly $5 million in Measure A bond money went to road construction (Bid Package 3), plus $987,611 for construction management and a CEQA exemption for Geer Road — part of $18.6 million budgeted for road work this year.
City Council - Feb 10, 2026
The council moved the roads program forward with a construction management contract amendment and put the Geer Road project out to bid.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Turlock
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.